Lead Time Improvement in Special Projects

About Project:

Challenge

Special projects by definition manage activities that not repetitive. So the firm establish the following goals for this area:

  • Improve airfreight lead time from USA 12%
  • Maintain the cost competitiveness.

Lead Time Reduction Objective

Solution

Building a control tower that work in 2 shifts 7 days a week, allow us:

  • Take advantage of working in the afternoon at the same time that suppliers in USA which means faster communication and accelerate shipments.
  • Using Fridays to speed shipments.
  • Sometimes we got to move materials before USA weekend, so the shipments was traveling during the weekend.

Value

Our solution delivered the following value:

  • Airfreight lead time from USA was improved 13%
  • No extra cost, because the control tower is part our standard service.
  • Avoiding project delays and the risk of penalties.
  • Better flexibility.
  • Higher customer satisfaction.